COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Construction of a road of the fourth category, v. Novaci-Mine circle PC Brod Gneotino

PROJECT DETAILS


Construction of an asphalt road from v. Novaci to the entrance of the mine circle in PC "Brod - Gneotino". The 11 km long road, width of 6 meters under asphalt and sidewalks of 75 cm from the left and from the right side.
Project timeline:
Start 15.04.2013
Anticipated end 15.08.2014
End 15.08.2014
Start date:
15.04.2013
End date:
15.08.2014
Completion date:
15.08.2014
Type of project:
Institution:
Non-Budget Users
Municipality:
Novaci
Budget program:
АКЦИОНЕРСКИ ДРУШТВА


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
1.6.9 Инсталирани капацитети за производство на електрична енергија од ветар167.754.000,000,00
Градење нови локални патишта (сите плански региони)167.754.000,00167.754.000,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Други извори 167.754.000,00Сопствени средства на АД ЕСМ
Република Северна Македонија Влада на Република Северна Македонија