COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

TILE AND ASPHALTING WORKS

PROJECT DETAILS


The road along the crown of the dam Mavrovo was built with the construction of the dam itself, made of lined granite cubes, with a two-sided slope. Over time, a number of installations such as plumbing and electricity have been maintained. telephony, etc. with which the excavation was carried out, the installations were installed and the cubes were rearranged. This disrupts the drainage of the dam itself, which causes larger overhangs on the crown itself, which causes problems on the downstream slope in terms of slipping of the humus part of the downstream slope. Due to the stated reasons, there was a need to remove the existing granite cubes, install all installations in concrete canals and canals, construction of a one-sided slope of the dam, construction of drainage leads to the upstream side and completely new asphalting.
Project timeline:
Start 10.07.2020
Anticipated end 23.08.2020
End 20.11.2020
Start date:
10.07.2020
End date:
23.08.2020
Completion date:
20.11.2020
Type of project:
Institution:
Non-Budget Users
Municipality:
Mavrovo and Rostushe
Budget program:
АКЦИОНЕРСКИ ДРУШТВА


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Осовременување на постојните локални патишта (сите плански региони)1.910.914,101.910.914,10


Indicators



Finance

Financing sourceInstitutionAmountNote
Други извори 1.910.914,10Сопствени средства на АД ЕСМ
Република Северна Македонија Влада на Република Северна Македонија