COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Design and construction of a six-seater cable car on Popova Sapka

PROJECT DETAILS


Design and construction of a six-seater cable car facility in the Popova Sapka ski resort, by putting it into trial operation and obtaining an approval for use. Purpose - modernization of the ski center and increase the capacity of skiers and ski slopes.
Project timeline:
Start 01.06.2016
Anticipated end 01.08.2017
End 13.02.2020
Start date:
01.06.2016
End date:
01.08.2017
Completion date:
13.02.2020
Type of project:
Institution:
Non-Budget Users
Municipality:
Tetovo
Budget program:
АКЦИОНЕРСКИ ДРУШТВА


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
1.6.9 Инсталирани капацитети за производство на електрична енергија од ветар581.002.500,000,00
Оптимално користење на природното богатство на регионите во функција на развој на туризмот581.002.500,00581.002.500,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Други извори 581.002.500,00Сопствени средства на АД ЕСМ
Република Северна Македонија Влада на Република Северна Македонија