COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Oslomej Photovoltaic Power Plant 1

PROJECT DETAILS


The project envisages construction of a photovoltaic power plant within REK Oslomej. The power plant will be built on a former tailings dump, which will recultivate the land. The power plant is expected to produce about 17GWh per year, enough for the needs of about 2800 households.
Project timeline:
Start 03.02.2020
Anticipated end
End 03.04.2021
Start date:
03.02.2020
End date:
03.04.2021
Completion date:
Type of project:
Institution:
Non-Budget Users
Municipality:
Kichevo
Budget program:
АКЦИОНЕРСКИ ДРУШТВА


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
1.6.3. Поттикнување на користењето на соларната енергија (сите плански региони)541.500.599,41241.543.000,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Други меѓународни извори 362.805.401,61ЕБОР
Други извори 178.695.197,81Сопствени средства на АД ЕСМ
Република Северна Македонија Влада на Република Северна Македонија