COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Park of wind power plants (PVE) Bogdanci - first phase

PROJECT DETAILS


The Bogdanci Wind Power Park project consists of: - installation of 22 x 2.3 MW (total 50 MW) wind turbines - construction of 20/110 kV SS Bogdanci - construction of 110 kV transmission line SS Bogdanci - SS Valandovo - construction of access roads - construction of a connecting transmission line field in 110/35/10 kV SS Valandovo Taking into account the available financial resources, it was agreed to install the wind farm in two phases: the first phase with 36.8 MW and net annual production of 100 GWh and the second phase with the remaining 13.8 MW and additional net production of 37 GWh. In the first phase, 16 wind turbines were installed. The volume of works from the project "Bogdanci Wind Power Park" was divided into three lots: LOT 1 - Includes construction of foundations, procurement and installation of wind turbines. LOT 2 - Includes construction of access roads and platforms for cranes, substation, 110kV transmission line Bogdanci - Valandovo. LOT 3 - Expansion of the substation in Valandovo - construction of transmission lines for connection.
Project timeline:
Start 01.06.2011
Anticipated end
End 19.09.2014
Start date:
01.06.2011
End date:
19.09.2014
Completion date:
Type of project:
Institution:
Non-Budget Users
Municipality:
Bogdanci
Budget program:
АКЦИОНЕРСКИ ДРУШТВА


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
1.6.9 Инсталирани капацитети за производство на електрична енергија од ветар3.444.958.778,623.444.958.778,62


Indicators



Finance

Financing sourceInstitutionAmountNote
Други меѓународни извори 2.957.231.639,71Развојна банка КФВ
Други извори 487.727.138,91Сопствени средства на АД ЕСМ
Република Северна Македонија Влада на Република Северна Македонија