COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Rehabilitation of a local road from the village of Sushichki Most to the landfill Rusino, Municipality of Gostivar - second phase

PROJECT DETAILS


The local road from the village of Sushichki Most to the Rusino landfill The Municipality of Gostivar is in a very difficult condition. The road has been built since the time of the former Yugoslavia, several interventions have been made but they have not solved the problems for better access to the regional landfill Rusino. The asphalt is completely depreciated, there are big holes in the road, some parts of the road are very difficult to cross, PCEs from the municipalities of PPR face very big problems when they bring the solid waste to the landfill. Due to the poor condition of the local road, the public utility companies from the municipalities of PPR are facing a number of defects and other additional costs for maintenance of the means of transport. Taking into account the above, the project is of great regional importance because the regulation and rehabilitation of a local road from the village of Sushichki Most to the landfill Rusino will solve a very big problem that has complicated the situation with the transportation and treatment of solid waste. level. Especially during the winter, when due to the poor access road to the Rusino landfill, the garbage could not be carried, so in many cases the garbage was thrown along the road, which narrowed the road and created additional difficulties for access to the regional landfill Rusino. Note: the project documentation was prepared with the funds of BRD from 2017. 2. Rehabilitation of a local road from the village of Sushichki most to the landfill Rusino Municipality of Gostivar: I. Prerequisites - Marking and securing the route (the axis of the subject location - from a tabular overview), - Clearing the route of bushes, roots, trees, etc. (computer measured), - Coating of vertical surfaces with unstable surfaces with unstable emulsion RB200, on an old joint with new asphalt (measured by computer). II.Upper machine - Procurement, transport and preparation of a buffer layer of crushed stone with grains F (0 - 63) mm, with planning and compaction to the required density d = 30cm below the road (to perform field testing for the position made according to MKS standards) (from tabular review), - Procurement, transport and machine installation and compaction of bituminized load-bearing abrasive layer BNHS 16A with thickness d = 7cm (to submit laboratory tests for the prepared position according to MKS standards) (measured by computer), - Construction of sidewalks and mechanical stabilization according to the project. The realization of this project will significantly contribute to the realization of one of the strategic goals of the Strategy for balanced regional development of the Republic of Macedonia.
Project timeline:
Start 06.07.2018
End 30.09.2019
Anticipated end 30.10.2020
Start date:
06.07.2018
End date:
30.10.2020
Completion date:
30.09.2019
Type of project:
Патен сообраќај
Institution:
Bureau for Regional Development
Municipality:
Gostivar
Budget program:
РЕГИОНАЛЕН РАЗВОЈ


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Подигнување на капацитетот на планските региони за препознавање, промовирање и реализирање на потенцијалот за инвестиции во планските региони25.810.428,0022.269.523,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаМИНИСТЕРСТВО ЗА ЛОКАЛНА САМОУПРАВА25.810.428,00 
Република Северна Македонија Влада на Република Северна Македонија