COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Reconstruction of the facade, floors and interior decoration in OOU Brača Miladinovci, Municipality of Struga

PROJECT DETAILS


Reconstruction of the facade, floors and interior decoration in OOU Brača Miladinovci, Municipality of Struga
Project timeline:
Start 01.01.2023
Anticipated end 31.12.2023
End
Start date:
01.01.2023
End date:
Completion date:
31.12.2023
Type of project:
Градба
Institution:
Ministry of Education and Science
Municipality:
Struga
Budget program:
ИНВЕСТИЦИИ ВО ОБРАЗОВАНИЕТО


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Development for infrastructure capacity of school objects41.084.733,0041.084.733,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаМИНИСТЕРСТВО ЗА ОБРАЗОВАНИЕ И НАУКА41.084.733,00 
Република Северна Македонија Влада на Република Северна Македонија