COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Procurement of substation for supply of electricity and procurement of photovoltaics for production of electricity for own needs

PROJECT DETAILS


Procurement of substation for supply of electricity and procurement of photovoltaics for production of electricity for own needs
Project timeline:
Start 01.01.2022
Anticipated end 31.12.2022
End
Start date:
01.01.2022
End date:
Completion date:
31.12.2022
Type of project:
Institution:
Government of the Republic of North Macedonia / FITD
Municipality:
Bitola
Budget program:
АДМИНИСТРАЦИЈА


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Introduction of certain measures (tax exemptions and similar incentives) to direct private investment to underdeveloped planning regions3.764.511,003.764.511,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаФонд за иновации и технолошки развој3.764.511,00 
Република Северна Македонија Влада на Република Северна Македонија