COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Streets in the city of Debar (newly designed street "1" "2", in Block 3 locality "A" foreseen by DUP)

PROJECT DETAILS


Construction of a branch on 8th Septemvri Street (from the Police Station building to the Mosque building with a clock tower facing boulevard 100) with a length of 298m, street profile 10m, roadway width 6m and sidewalks 2x 2 m. According to DUP for part of Block 3 locality "A" (Newly planned street "1" with a length of 80 m. and a profile of 14.2 m. with a roadway width of 6 m and sidewalks 1x 1.5 + 1x5, 7m).
Project timeline:
Start 01.01.2022
Anticipated end 22.06.2022
End
Start date:
01.01.2022
End date:
Completion date:
22.06.2022
Type of project:
Водовод и канализација
Institution:
Ministry of Transport and Communications
Municipality:
Debar
Budget program:
УРБАНИЗАМ И ГРАДЕЖНИШТВО


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Consistent application of the Law on Balanced Regional Development (*) regarding the allocation of funds for regional development in the amount of at least 1% of GDP6.167.426,606.167.427,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаМИНИСТЕРСТВО ЗА ТРАНСПОРТ И ВРСКИ6.167.426,60 
Република Северна Македонија Влада на Република Северна Македонија