Basic project for the construction of a pipeline for fecal sewage - part of the village of Veleshta - Struga Municipality

PROJECT DETAILS


Basic project for the construction of a pipeline for fecal sewage - part of the village of Veleshta - Struga Municipality
Project timeline:
Start 01.01.2021
Anticipated end 31.12.2021
End
Start date:
01.01.2021
End date:
Completion date:
31.12.2021
Type of project:
Градба
Institution:
Ministry of Local Self-Government
Municipality:
Struga
Budget program:
РЕГИОНАЛЕН РАЗВОЈ


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Обезбедување погодна деловна клима во планските региони1.074.171,001.074.171,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаМИНИСТЕРСТВО ЗА ЛОКАЛНА САМОУПРАВА1.074.171,00 