COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Reconstruction of the water supply network, fecal and storm sewerage in Resеnska St. 1-2

PROJECT DETAILS


Reconstruction of the water supply network, fecal and storm sewerage in Resanska St. 1-2
Project timeline:
Start 01.01.2021
Anticipated end 31.12.2021
End
Start date:
01.01.2021
End date:
Completion date:
31.12.2021
Type of project:
Градба
Institution:
Ministry of Local Self-Government
Municipality:
Chair
Budget program:
РЕГИОНАЛЕН РАЗВОЈ


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Обезбедување погодна деловна клима во планските региони4.941.917,004.941.917,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаМИНИСТЕРСТВО ЗА ЛОКАЛНА САМОУПРАВА4.941.917,00 
Република Северна Македонија Влада на Република Северна Македонија