COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Reconstruction of the primary school "Rexho Rushit Zajas" in the village. Collars

PROJECT DETAILS


Reconstruction of the primary school "Rexho Rushit Zajazi" in the village of Kolari for the purpose of safety, conditions and energy efficiency. Things envisaged by this project are removal of the existing roof structure that is dilapidated and unsafe where a new roof structure is envisaged. the façade walls or the building is thermally insulated
Project timeline:
Start 12.06.2020
End 25.11.2020
Anticipated end 30.11.2020
Start date:
12.06.2020
End date:
30.11.2020
Completion date:
25.11.2020
Type of project:
Градба
Institution:
Bureau for Regional Development
Municipality:
Kichevo
Budget program:
РЕГИОНАЛЕН РАЗВОЈ


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Подигнување на капацитетот на планските региони за препознавање, промовирање и реализирање на потенцијалот за инвестиции во планските региони1.052.870,001.043.194,00


Indicators



Finance