COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT
Construction of main gas pipeline, section 2 "Negotino (Kavadarci) - Bitola"
PROJECT DETAILS
Construction of a main gas pipeline, section 2 "Negotino (Kavadarci) - Bitola", technical parameters as follows: • Line section in the length of 92 km with pipe diameter DN 500 (20 ”), • Block stations: BS (DN500) com 5, BS (DN200) com 2, BS (DN150) and BS (DN80) • Reception cleaning station DN 500, • GMRS "Feni Industries", with a capacity of Q = 15 000 m3 / h • GMRS "Prilep", with a capacity Q = 24 000 m3 / h • GMRS "Bitola", with capacity Q = 28 000 m3 / h
Project timeline:
Start date:
17.02.2017
End date:
Completion date:
Type of project:
Institution:
Non-Budget Users
Municipality:
Kavadarci
Budget program:
АКЦИОНЕРСКИ ДРУШТВА