COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Rehabilitation of the high school Ljupcho Santov, Kocani

PROJECT DETAILS


Rehabilitation of the high school Ljupcho Santov, Kocani
Project timeline:
Start 01.07.2019
Anticipated end 31.12.2019
End
Start date:
01.07.2019
End date:
Completion date:
31.12.2019
Type of project:
Градба
Institution:
Ministry of Education and Science
Municipality:
Kochani
Budget program:
ИНВЕСТИЦИИ ВО ОБРАЗОВАНИЕТО


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Development for infrastructure capacity of school objects350.941,00350.941,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаМИНИСТЕРСТВО ЗА ОБРАЗОВАНИЕ И НАУКА63.169,00 
Други меѓународни извориМИНИСТЕРСТВО ЗА ОБРАЗОВАНИЕ И НАУКА287.772,00 