COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Rehabilitation of the primary school Krste Petkov Misirkov Orizari Kocani

PROJECT DETAILS


Rehabilitation of the primary school Krste Petkov Misirkov Orizari Kocani
Project timeline:
Start 04.03.2021
End 21.04.2021
Anticipated end 04.05.2021
Start date:
04.03.2021
End date:
04.05.2021
Completion date:
21.04.2021
Type of project:
Градба
Institution:
Ministry of Education and Science
Municipality:
Kochani
Budget program:
ИНВЕСТИЦИИ ВО ОБРАЗОВАНИЕТО


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Development for infrastructure capacity of school objects4.125.358,004.125.358,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаМИНИСТЕРСТВО ЗА ОБРАЗОВАНИЕ И НАУКА1.954.915,00 
Други меѓународни извориМИНИСТЕРСТВО ЗА ОБРАЗОВАНИЕ И НАУКА2.170.443,00 
Република Северна Македонија Влада на Република Северна Македонија