COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Construction and equipping of a school sports hall in the primary school Naim Frasheri v. Morane, Studenicani

PROJECT DETAILS


Construction and equipping of a school sports hall in the primary school Naim Frasheri v. Morane, Studenicani
Project timeline:
Start 15.10.2021
Anticipated end
End
Start date:
15.10.2021
End date:
Completion date:
Type of project:
Градба
Institution:
Ministry of Education and Science
Municipality:
Studenichani
Budget program:
ИНВЕСТИЦИИ ВО ОБРАЗОВАНИЕТО


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Designing a model for distribution of investment programs (capital investments) in primary and secondary education as a systemic solution by which the funds for construction and reconstruction (rehabilitation) of school buildings, especially toilets, gyms, etc., would be determined, taking take into account the Development Index of the planning regions.6.371.907,006.371.907,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаМИНИСТЕРСТВО ЗА ОБРАЗОВАНИЕ И НАУКА1.695.754,00 
Други меѓународни извориМИНИСТЕРСТВО ЗА ОБРАЗОВАНИЕ И НАУКА4.676.153,00 
Република Северна Македонија Влада на Република Северна Македонија