Construction and equipping of a school sports hall in the primary school 7 Marsi, Opae, Lipkovo

PROJECT DETAILS


Construction and equipping of a school sports hall in the primary school 7 Marsi, Opae, Lipkovo
Project timeline:
Start 25.12.2019
Anticipated end 30.12.2020
End
Start date:
25.12.2019
End date:
Completion date:
30.12.2020
Type of project:
Градба
Institution:
Ministry of Education and Science
Municipality:
Lipkovo
Budget program:
ИНВЕСТИЦИИ ВО ОБРАЗОВАНИЕТО


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Designing a model for distribution of investment programs (capital investments) in primary and secondary education as a systemic solution by which the funds for construction and reconstruction (rehabilitation) of school buildings, especially toilets, gyms, etc., would be determined, taking take into account the Development Index of the planning regions.2.224.049,002.224.049,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаМИНИСТЕРСТВО ЗА ОБРАЗОВАНИЕ И НАУКА961.242,00 
Други меѓународни извориМИНИСТЕРСТВО ЗА ОБРАЗОВАНИЕ И НАУКА1.262.807,00 