COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Construction of water supply system for the villages G. Zrkle, Sushica, Inche, monastery of St. Bogorodica and Gorni and Dolni Manastirec, O. Makedonski Brod

PROJECT DETAILS


Construction of water supply system for the villages G. Zrkle, Sushica, Inche, monastery of St. Bogorodica and Gorni and Dolni Manastirec, O. Makedonski Brod
Project timeline:
Start 16.01.2019
Anticipated end
End
Start date:
16.01.2019
End date:
Completion date:
Type of project:
Водовод и канализација
Institution:
Ministry of Transport and Communications
Municipality:
Makedonski Brod
Budget program:
УРБАНИЗАМ И ГРАДЕЖНИШТВО


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Обезбедување погодна деловна клима во планските региони29.972.611,0029.972.611,00


Indicators



Finance

Република Северна Македонија Влада на Република Северна Македонија