COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Construction of part of the fecal sewerage village Vakcince, municipality of Lipkovo

PROJECT DETAILS


Defining the problem and its assessment, Considering the time we live in, XXI century, it is unfortunate not to have fecal sewage, when it is known that without proper infrastructure, asphalt roads, water supply and especially sewerage, no development of the area is possible, Citizens regularly come to the Municipality to complain, because either the neighbor or anyone else throws wastewater in the street, so they ask us to do something. Secondly, we are advised by the health authorities to build the sewerage as soon as possible, because from the wastewater, the septic tanks that some of the rich have, from drinking water from the wells, there has been a great infection, bacteriological, etc., so is a record area in the country with pollution and a large number of pollution diseases. The assessment is that this problem will be solved once and for all, vital for the area, from any aspect, for example, the realization will stop the migration abroad, which at the moment can be freely said that we are leaders, but of course it is not for something good, which means the situation is very bad. By investing in infrastructure, both domestic and foreign investors will invest. Condition of the target area, The area, v. Vaksince is an area with specific needs, which currently, at a distance of 10 km from the seat of the Municipality, and also in the middle of this village passes the regional road v. Vaksince-v. Lojane-Border with the Republic of Serbia (v. Miratovac) , a road that apart from connecting the Municipality of Lipkovo and the region with the south of Serbia, connects the region from the Presevo Valley with the capital, Skopje, so with this there will be more households that will be able to use it. Therefore, we as a Municipality give preference to this settlement as soon as possible to finally complete at least the main network, because the secondary network, we Municipality in cooperation with the residents will realize and finally solve a large project for those residents, the Municipality and the region.
Project timeline:
Start 17.07.2019
Anticipated end 30.11.2019
End 22.01.2020
Start date:
17.07.2019
End date:
30.11.2019
Completion date:
22.01.2020
Type of project:
Израдба на капацитети
Institution:
Bureau for Regional Development
Municipality:
Lipkovo
Budget program:
РЕГИОНАЛЕН РАЗВОЈ


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Подигнување на капацитетот на планските региони за препознавање, промовирање и реализирање на потенцијалот за инвестиции во планските региони2.456.194,002.455.256,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаБИРО ЗА РЕГИОНАЛЕН РАЗВОЈ24.531.553,00 
Република Северна Македонија Влада на Република Северна Македонија